Classrooms to be renovated with Higher Education Bond funding

 

Building Name

Whole Building Renovation/

Classrooms only/

Room #s

Budget

Advertise for designer

Bid Date

ConstructionDates

(CIP website)

ConstructionDates (classroom offline)

Faculty

Liaison

Project Manager

Designer

Phase of Construction

Arts Commons

 

$25,003,342

3/15/04

11/20/06

1/07 – 9/08

 

 

C. Acquesta

Polshek Partnership

 

Coker Hall &

Mitchell Hall

GPC/201 (198)*

$448,473

12/31/03

6/7/05

4/05 – 8/05

Spring ’05 - Summer ‘05

To be announced

Michael Pierce

Hager Smith

Programming

GPC/205 (58), 305 (28), 9 (30), 106 (20)

$612,428

12/31/03

4/25/05

5/06 – 7/06

Spring ’06 -  Summer ‘06

 

Michael Pierce

Hager Smith

Programming

Davie Hall- On Hold

GPC/101 (45),112 (90),301 (45), elev, stairs

$1,292,417

No date available

2/22/05

6/05 – 3/06

Summer ’05 - Spring ‘06

Bill Ware

Michael Pierce

Davis Kane

Programming

Fetzer Gym

GPC/104 (46),105 (8),106 (80),109 (187)

$495,422

No date available

9/20/04

5/05 – 7/05

Spring ’05 - Summer ‘05

Deb Bialeschki

Michael Pierce

Davis Kane

Construction Documents

Global Education

GPC/1005, 1009, 3024, 3033B, 1015, non-GPC (conference rooms)/ 2008, 2010, 3009, 4003

$30,200,000

2/25/02

To Be Determined

9/04 -9/06

Fall ’04 – Fall’06

 

Diane Gillis

Leers Weinzapfel

Construction Documents (May 22 Submit)

Greenlaw Phase I

101 (176), 222 (48), 301 (35), 302 (35), 304 (35), 305 (35), 321 (15), 431 (114), lobbies

$1,825,000

3/1/04

8/2/05

5/07 – 7/07

Spring ’07 - Summer ‘07

Todd Taylor

Diane Gillis

Interview May 4

Short List

Greenlaw Phase II (rolling)

103 (25), 104 (25), 106 (25), 107 (25), 317 (34), 318 (34), 319 (35), 526A (15)

 

These classrooms are MML-0.  Start in summer ’05 and be on a rolling schedule, worked in as space is available per the Registrar.

Todd Taylor

 

 

 

Hamilton I

100 (442), 150 (20), 351 (32), ext. ramps, 3rd floor corridor

$1,539,000

1/12/04

2/1/06

6/05 – 12/05

Summer ’05 – Fall ‘05

Jean DeSaix

Jerry Guerrier

Hoke/New Vision

Programming

Hamilton II

420 (22), 423 (20), 425 (20), 452 (30), 470 (30), 517 (22), 519 (10), 523 (22), 570 (15) (non GP)

?

10/05 (?)

2/28/06

6/06 – 12/06

Summer ’06 – Fall ‘06

Jean DeSaix

 

 

 

Hanes Hall- Complete Building Renovation

WB/GPC/103 (42),108 (42),306 (35),307 (45),308 (45), possible 107 (now a storage room)

$5,034,713

4/15/04

To Be Determined

Has to Follow SASB, which is scheduled for completion Fall ‘06

David Lanier

Diane Gillis

Advertising May 3

 

Howell Hall

GPC/100,104 (192), 106 (35), 107 (40), 201 (25), 203 (60), 207, stairs, elevator

Will this become a total building renovation?

 

 

 

 

Manning Hall

GPC/209 (188), 307 (60), 208, 304

$721,619

*$400,000 +/- needed for DOI Requirements

No Date Available

6/21/05

10/05 – 3/07

Spring ’05 – Summer ’05 (?)

Larry Rowan

Michael Pierce

Davis Kane

Programming

New West

WB/212(gp) (51),104 (ngp)(20)

$4,275,000

1/17/03

6/10/04

7/04 – 1/06

Summer ’04 – Spring ‘06

 

Paul Kapp

Hagersmith Architecture

Bidding

Phillips Hall

GPC/212 (24), 220 (27), 222 (28), 228 (40),  301 (20), 330 (64), 332 (77)

$1,431,828

5/10/04

4/15/05

5/05 – 9/05

 

 

Diane Gillis

Aggie Crews

Bid Phase (April 20)

Saunders Hall

WB/112 (73), 201 (36), 212 (89), 215 (36), 306 (89)

$3,470,300

 

9/02

11/03 – 11/04

 

 

Paul Kapp

Walter Robs Callahan & Pierce

Construction Administration

Playmakers &

Gerrard Hall

WB

$1,787,440

2/04

6/05

6/05 – 7/06

Summer ’05 – Summer ‘06

 

Paul Kapp

Ann Beha, Architects

Programming

WB

$1,350,000

6/3/03

3/30/05

6/05 – 7/06

Summer ’05 – Summer ‘06

 

Paul Kapp

Ann Beha, Architects

Programming

Steele Building

WB

   $3,428,600

3/18/04

9/19/06

10/06 – 3/08

 

 

Paul Kapp

Bovey

Designer

Wilson Hall

WB/107 (150), 128 (86), 139 (25), 202 (45), 217 (50)

$8,920,000

9/15/03

7/14/05

10/05 – 12/06

6/05-8/06

Todd Taylor

Diane Gillis

Little Diversified Architectural Consultant

Programming Unassigned because CDAC Rep did not show up to the meeting

*Indicates seat count for the room

 

 

 

 

Buildings Removed from Schedule

 

Building Name

Whole Building Renovation/

Classrooms only/

Room #s

Budget

Advertise for designer

Bid Date

ConstructionDates

(CIP website)

ConstructionDates (classroom schedule)

Faculty Liaison

Project Manager

Designer

Phase of Construction

Alumni Hall

GPC/203 (50),205 (55),207 (40),308 (25)

$1,180,615

3/15/02

8/11/03

9/03 – 11/03

207: 8/00-12/00

203, 205: 8/03– 8/04

308: 1/02- 5/02

 

Paul Kapp

Davis Kane Architects

Completed

Hill Hall

NGPC/ 103, 202, 205, 206, 207

+acoustic upgrade of rehearsal space

$1,110,930

12/31/03

6/15/05

On hold

On hold pending Arts Common Study

 

Paul Kapp

Davis Kane Architects

 

Woollen Gym

*Classroom project revised to redoing gym floor (gym is used as a classroom)

$712,500

?

3/04

Code Analysis Underway

303, 304: 1/04-1/05

301A, 301B, 302: 1/05-1/06

 

Michael Pierce

 

 

 

Buildings Completed

 

Building Name

Whole Building Renovation/

Classrooms only/

Room #s

Budget

Advertise for designer

Bid Date

ConstructionDates

(CIP website)

ConstructionDates (classroom schedule)

Faculty Liaison

Project Manager

Designer

Phase of Construction

Caldwell Hall-Completed

GPC/103 (40),105 (73),208 (20)

$606,200

 

12/01

1/02 - 11/02

1/01- 8/01

 

 

 

 

Murphey Hall

WB/100 (45), 102 (28), 103 (18), 105 (21), 107 (45), 108 (47), 109 (16), 111 (209),112 (40), 113 (24), 215 (38), 217 (45), 301 (28), 305 (30), 306, 314 (25)

$6,723,500

 

4/01

6/01 – 11/02

6/01-12/02

 

 

 

 

Peabody Hall

WB/10 (43), 104 (149), 203 (39), 204 (45), 215 (44), 216 (45), 217 (40), 218 (50), 220 (40), 306 (45), 311 (45)

$9,049,608

 

2/01

5/02 – 1/04

6/02-12/03

 

Peter Krawchyk

 

 

Phillips Hall

247 (57), 265 (95), 367 (49), 381 (42), 383 (62)

Already renovated